News
July 15, 2024

Winter Blues on the Jobsite: No Relief for Contractor Hit with Acceleration Costs

Imagine this: you're contracted for a construction project, and delays pile up due to factors outside your control. Now, the pressure's on to finish the job quickly, often in harsher conditions, leading to additional costs. But wait, your contract includes a "no damages for delay" (NDD) clause, meaning you can't recoup those extra expenses. This is the unfortunate reality a subcontractor, Luse, faced in a court case.

The Case: A Race Against Time, Not Winter

Luse was subcontracted for pipe insulation on a large industrial project. The project encountered delays beyond Luse's control. Facing a revised deadline, the general contractor, Graycor, requested Luse ramp up its workforce and complete the work in a shorter timeframe—during the winter. This meant battling harsh weather conditions, leading to lower productivity, worker fatigue, and ultimately, higher costs for Luse.

The Legal Battle: Acceleration vs. Delay Damages

Luse argued that these additional costs stemmed from "acceleration," a separate issue from the initial delays, and therefore shouldn't be subject to the NDD clause. However, the court sided with Graycor. Their reasoning? The acceleration was a consequence of the initial delays, making Luse ineligible for compensation.

Furthermore, Luse couldn't claim reimbursement under the project's change order clause. This clause required written authorization for any scope or condition modifications, which Luse lacked for the accelerated work schedule.

The Contractor's Dilemma: Stuck Between a Rock and a Hard Place

This case highlights the potential unfairness of NDD clauses. Contractors can end up absorbing unforeseen expenses due to delays outside their control. Here's how to navigate this tricky situation:

  • Negotiate, Negotiate, Negotiate: Before signing any contract, meticulously review the clauses, particularly the NDD. If possible, negotiate its removal or modification to allow for recovery of reasonable acceleration costs.
  • Subcontractors Beware: Be mindful of NDD clauses potentially present in the prime contract that "flow down" to subcontractors. Understand their implications before agreeing to any subcontract terms.
  • The Art of Communication: Open communication with the general contractor is vital. Document all discussions regarding adjustments to the schedule and ensure proper authorization for any changes in work scope or conditions.

The Road Ahead: A Sticky Situation with Unclear Solutions

The court's decision offers no clear guidance on how contractors can protect themselves when pressured to accelerate work under NDD clauses. Should they refuse to comply without a written change order, potentially jeopardizing the project timeline? Or should they demand a time extension, which might not be feasible?

This lack of clear direction leaves contractors in a difficult position.  The possibility of Luse appealing the decision to the state supreme court suggests there may be more to this story.  In the meantime, the construction industry continues to grapple with the complexities of NDD clauses and the burden they place on contractors facing unforeseen challenges.

News
July 15, 2024

Winter Blues on the Jobsite: No Relief for Contractor Hit with Acceleration Costs

No items found.

Imagine this: you're contracted for a construction project, and delays pile up due to factors outside your control. Now, the pressure's on to finish the job quickly, often in harsher conditions, leading to additional costs. But wait, your contract includes a "no damages for delay" (NDD) clause, meaning you can't recoup those extra expenses. This is the unfortunate reality a subcontractor, Luse, faced in a court case.

The Case: A Race Against Time, Not Winter

Luse was subcontracted for pipe insulation on a large industrial project. The project encountered delays beyond Luse's control. Facing a revised deadline, the general contractor, Graycor, requested Luse ramp up its workforce and complete the work in a shorter timeframe—during the winter. This meant battling harsh weather conditions, leading to lower productivity, worker fatigue, and ultimately, higher costs for Luse.

The Legal Battle: Acceleration vs. Delay Damages

Luse argued that these additional costs stemmed from "acceleration," a separate issue from the initial delays, and therefore shouldn't be subject to the NDD clause. However, the court sided with Graycor. Their reasoning? The acceleration was a consequence of the initial delays, making Luse ineligible for compensation.

Furthermore, Luse couldn't claim reimbursement under the project's change order clause. This clause required written authorization for any scope or condition modifications, which Luse lacked for the accelerated work schedule.

The Contractor's Dilemma: Stuck Between a Rock and a Hard Place

This case highlights the potential unfairness of NDD clauses. Contractors can end up absorbing unforeseen expenses due to delays outside their control. Here's how to navigate this tricky situation:

  • Negotiate, Negotiate, Negotiate: Before signing any contract, meticulously review the clauses, particularly the NDD. If possible, negotiate its removal or modification to allow for recovery of reasonable acceleration costs.
  • Subcontractors Beware: Be mindful of NDD clauses potentially present in the prime contract that "flow down" to subcontractors. Understand their implications before agreeing to any subcontract terms.
  • The Art of Communication: Open communication with the general contractor is vital. Document all discussions regarding adjustments to the schedule and ensure proper authorization for any changes in work scope or conditions.

The Road Ahead: A Sticky Situation with Unclear Solutions

The court's decision offers no clear guidance on how contractors can protect themselves when pressured to accelerate work under NDD clauses. Should they refuse to comply without a written change order, potentially jeopardizing the project timeline? Or should they demand a time extension, which might not be feasible?

This lack of clear direction leaves contractors in a difficult position.  The possibility of Luse appealing the decision to the state supreme court suggests there may be more to this story.  In the meantime, the construction industry continues to grapple with the complexities of NDD clauses and the burden they place on contractors facing unforeseen challenges.